GR was contracted to design, supply and install this 30m x 2.5m steel truss bridge. The site was particularly complex due to overhead power-lines, underground services, main road restrictions and crane access. To overcome these obstacles GR used bored piers at one end to avoid underground services, shut down the power to the street on a Saturday for the bridge placement. Other elements to the project were, rock beaching, approach paths, precast concrete decking.